By Kajal Rajpoot · Reviewed by Arshi Chadha, Founder
Solar Panel Installation in Faridabad: Cost, DHBVN Net Metering & PM Surya Ghar Subsidy

- •System size: 2 kW to 10 kW (Typical Residential)
- •Cost after subsidy: ₹56,000 – ₹4.72 Lakh
- •Monthly savings: ₹2,800 – ₹10,500 (at DHBVN ₹7.5/unit)
- •Payback period: 3.5 – 5 years
- •Subsidy (3 kW): ₹78,000 central only — Haryana has no state top-up
Faridabad sits on the DHBVN grid, the same Haryana distribution utility that powers Gurugram. The good news: net metering paperwork moves faster here than in either BSES Delhi or PVVNL UP. The honest news: Haryana does not offer a state-level solar subsidy. Anyone quoting "₹1.08 Lakh stacked subsidy" or "double subsidy" for a Faridabad home is either copy-pasting Delhi/UP marketing or actively misleading you.
This guide walks through the real 2026 cost, the central-only PM Surya Ghar subsidy math, and how DHBVN net metering actually works for Sector 21, Greater Faridabad, or a NIT plot.
Why the Subsidy Math is Different in Faridabad
Faridabad is in Haryana. Haryana has zero state-level solar subsidy. The only incentive available is the central PM Surya Ghar Muft Bijli Yojana — capped at ₹78,000 for a 3 kW residential system.
Compare with neighbours:
- Noida (UP): ₹78,000 central + ₹30,000 UP state = ₹1,08,000
- Delhi (BSES/TPDDL): ₹78,000 central + up to ₹30,000 Delhi state + GBI on generation
- Faridabad (DHBVN): ₹78,000 central — that's the entire stack
This isn't a flaw in your roof or your bill. It's a structural fact of where the Haryana–Delhi border falls. The same 3 kW system that nets ₹1.08L of incentive across the Yamuna nets ₹78,000 here. Pretending otherwise leads to budget shortfalls when the disbursal cheque arrives.
If you've read Gurugram solar pricing, the Faridabad numbers will look familiar — same DHBVN process, same central-only subsidy.
Solar Installation Cost in Faridabad (2026)
We price every Faridabad installation off the same N-Type TOPCon module catalogue used across Delhi NCR — 580 Wp to 620 Wp Tier-1 panels, IEC-certified inverters, and DCR-compliant structures that pass DHBVN inspection on the first visit.
| System Size | Best For | Gross Cost (₹) | PM Surya Ghar Subsidy | Net Cost (₹) |
|---|---|---|---|---|
| 2 kW | 1–2 BHK, ~250 units/mo | 1,34,000 | 60,000 | 74,000 |
| 3 kW | 2–3 BHK, ~400 units/mo | 2,01,000 | 78,000 | 1,23,000 |
| 5 kW | 3 BHK villa, ~600 units/mo | 3,35,000 | 78,000 | 2,57,000 |
| 10 kW | Large villa / small commercial | 5,50,000 | 78,000 | 4,72,000 |
Costs use the live Bridgeway tier card: ₹67,000/kW for systems up to 5 kW, dropping to ₹55,000/kW above 5 kW.
DHBVN Net Metering: What Actually Happens
Net metering in Faridabad runs through DHBVN (Dakshin Haryana Bijli Vitran Nigam). The same utility that handles Gurugram, and arguably the cleanest net-metering workflow in the NCR. Typical timeline: 30–40 working days from application to meter installation.
- Empanelled vendor only. PM Surya Ghar requires a MNRE-empanelled installer. Bridgeway is empanelled; verify any quote you receive.
- Online application through the PM Surya Ghar portal — this triggers both the central subsidy claim and the DHBVN net meter request in one filing.
- Site feasibility by DHBVN engineer (typically within 7–10 days).
- Installation + commissioning — 2 to 4 days of on-site work.
- Net meter installation by DHBVN after inspection.
- Subsidy disbursal to your bank account within 30 days of commissioning.
If your installer asks you to "manage the portal yourself" — that's the moment to walk away. Subsidy filing is the install company's job.
The ₹78,000 Subsidy, Decoded
For a 3 kW system in Faridabad:
- First kW: ₹30,000
- Second kW: ₹30,000
- Third kW: ₹18,000
- Total: ₹78,000
That's the number to write on your back-of-envelope. There is no Haryana state component. There is no GBI in Haryana (GBI is a Delhi-only programme). Anyone quoting more than ₹78,000 of subsidy for a 3 kW Faridabad system is wrong — and you should ask for the official scheme order they're citing.
Talk to a solar engineer — not a salesperson
No forms, no spam. Just a quick WhatsApp chat with someone who actually knows solar.
Typically replies within 15 minutes during business hours
See your exact subsidy after state stacking
Payback Math for a Faridabad Household
Take the 3 kW case at ₹1,23,000 net cost.
A 3 kW system in Faridabad's irradiance band generates roughly 4,500 units a year. At DHBVN's ₹7.5/unit effective tariff for households on the upper slab, that's ₹33,750 of annual electricity offset.
Payback: ₹1,23,000 ÷ ₹33,750 ≈ 3.6 years.
Slightly longer than Noida (3 years) because the upfront cost is higher without the state subsidy. After payback, you're looking at 21+ years of essentially free generation. Panels carry a 25-year linear performance warranty; the inverter is replaced once around year 10–12.
For exact numbers on your bill and roof orientation, run the calculator — it pulls live DHBVN tariffs and the same subsidy table used in this article.
Best Areas for Solar in Faridabad
Independent floors and villas in Sectors 14, 15, 21, 28, 37, 46, and the Greater Faridabad belt (Sectors 75–89) typically have the unshaded rooftop area for a 3–10 kW system. NIT plots and older Old Faridabad housing often have shading from adjacent buildings — site survey is critical.
Apartment resident? You'll need RWA approval, and an RWA-level community installation is usually a better path. We've documented that route in our RESCO vs Community Solar guide.
What Could Go Wrong
A short, honest list:
- Vendors quoting "Haryana stacked subsidy." This does not exist. Walk away from any quote that includes a "state portion" for Faridabad.
- Subsidy delay. Disbursal is in theory 30 days from commissioning. In practice 30–60 days during portal congestion. Don't pay your vendor the full amount expecting subsidy will arrive on time.
- Net meter delay. DHBVN is the fastest NCR utility, but delays still happen during peak install season (March–June). Plan for 30–40 working days.
- Cheap module substitution. "₹50,000/kW" quotes are almost always older Mono PERC, not the N-Type TOPCon required for current PM Surya Ghar DCR compliance. The cheap quote becomes a non-disbursing subsidy.
- Industrial dust. Faridabad's industrial belt means panels soil ~25% faster than residential Delhi. Budget for quarterly cleaning, not annual.
FAQ
Does Faridabad qualify for the Haryana state solar subsidy? There is no Haryana state solar subsidy. The state government has not implemented a top-up over the central PM Surya Ghar scheme. Only the central ₹78,000 (for a 3 kW system) applies.
Is solar still worth it in Faridabad without a state subsidy? Yes. Payback is ~3.6 years on a 3 kW system, followed by 20+ years of nearly-free generation. The economics are excellent — they're just not quite as aggressive as Noida.
Will Haryana introduce a state subsidy in 2026? We won't speculate. As of publication, no Haryana state subsidy exists. If one is announced, we'll update this page and the Subsidy Guide within 48 hours.
Is the DHBVN process the same in Faridabad and Gurugram? Yes. Same utility, same portal, same timelines. A vendor who works one city can work the other.
Get a Site-Specific Quote
The numbers in this article are real and verified — but your roof, your shading, and your actual bill structure determine what you'll save. Drop your details and we'll come measure your rooftop. Free, no obligation, MNRE-empanelled.
Every 1 kW of solar on your roof offsets 1.5 tonnes of CO₂ per year
That's 40 trees planted — every year, for 25 years.
A typical 5 kW home system offsets 187 tonnes of carbon over its lifetime. That's equivalent to taking 8 cars off the road.
See your impact →How much can you save with solar?
Enter your electricity bill → get system size, subsidy amount & payback period
Get StartedLiked this article? Get a free solar quote
Tell us about your rooftop — we'll call with exact savings for your home.
Related Articles
How Rooftop Solar Can Eliminate Your Electricity Bill
Discover how Net Metering and PM Surya Ghar subsidies can reduce your monthly electricity bill to near-zero. Learn about system sizing, costs, and real-world savings.
Read moreSolar Installation Cost in Delhi NCR 2026: 3 kW at ₹1.32L net
Updated 2026 guide to solar costs in Delhi NCR. Learn about PM Surya Ghar subsidies, system pricing from 1kW-10kW, and how to reach zero electricity bills.
Read moreWhat Is Captive Open Access Solar (100% Equity Model)
Learn how Captive Open Access Solar (100% Equity Model) helps Indian businesses cut electricity costs by 40% using off-site solar plants. Guide on rules, savings & ROI.
Read moreRelated guides
Delhi Electricity Rate 2026
BSES & Tata Power per-unit rates, PPAC, subsidy — sourced from DERC.
ExploreRooftop Solar for Homes
Sizes, pricing & subsidy for every home rooftop in India.
Explore3 kW Solar Panel Price 2026
Real net price after PM Surya Ghar + state subsidy across 5 cities.
ExploreSolar Panel Generation per kW (India)
Units a 1 / 3 / 5 / 10 kW system actually produces — by city, by season.
ExploreSolar for Large Homes (5-10 kW)
Mid-size rooftops: sizing, financing & payback in Delhi NCR.
ExploreSolar for Farmhouses
10-25 kW hybrid systems for farmhouses with backup needs.
Explore