    BRPL Net Metering Process for Rooftop Solar in Delhi (2026)

    BRPL (BSES Rajdhani Power Limited) net metering is the regulatory process by which a rooftop solar system in south and west Delhi is connected to the BRPL grid via a bidirectional meter, allowing the consumer to export surplus generation and receive credit on their electricity bill. The full process — from application to net-meter commissioning — typically takes 30-45 days when paperwork is in order.</br>

    Last verified: 20 Mar 2026Verified by Bridgeway Power

    BRPL net metering — fees, timelines, eligibility

    Source: Bridgeway Power facts registry · Last verified 20 Mar 2026

    Eligible system size (residential)
    1 kW to 10 kW under PM Surya Ghar; up to sanctioned load otherwise
    Eligible system size (commercial)
    Up to 100% of sanctioned load via net metering; gross metering above
    Net meter cost
    Borne by consumer, typically Rs. 6,000-12,000 depending on meter type
    Application fee
    Rs. 500 (registration), refundable if rejected
    Technical feasibility timeline
    7-14 days from complete application
    Net meter installation timeline
    10-20 days post commissioning request
    Total process timeline
    30-45 days when documentation is complete
    Export tariff
    Per DERC retail tariff order — credited against import units, settled annually
    DISCOM portal
    https://www.bsesdelhi.com/web/solar

    BRPL net metering — end-to-end process (6 steps)

    1. 01

      Online application

      Apply via BRPL solar portal with CA number, sanctioned load, proposed system size, and uploaded documents (Aadhaar, bill, ownership proof, rooftop photos).

    2. 02

      Technical feasibility study

      BRPL engineer inspects the rooftop, transformer loading, and proposed inverter location. Issues TFR (Technical Feasibility Report) — 7-14 days.

    3. 03

      Vendor agreement and installation

      Consumer selects a DISCOM-empanelled vendor. Bridgeway is BRPL-empanelled. Installation typically takes 3-5 days.

    4. 04

      Pre-commissioning inspection

      BRPL re-inspects the installed system for compliance with safety codes (earthing, lightning arrestor, anti-islanding inverter). Issues clearance.

    5. 05

      Net meter installation

      BRPL installs the bidirectional net meter. The existing single-direction meter is removed. 10-20 days from clearance.

    6. 06

      Commissioning certificate

      BRPL issues the formal commissioning certificate. The certificate triggers PM Surya Ghar subsidy disbursal via DBT within 30 days.